BECKER, Minn. (AP) -- Xcel Energy Inc. says it will cost as much as $200 million to repair the damage from a catastrophic turbine failure at Minnesota's largest power plant last November.

Sherco plant director Ron Brevig says Xcel still hasn't determined exactly why turbine broke up, sending debris and metal flying and sparking a fire. Nobody was injured. He says consultants are expected to finish the investigation around the end of this year.

Brevig says most repair costs will be covered by insurance. He told reporters Wednesday that Xcel and contractors are working around the clock to complete the repairs so Unit 3 can restart in the first quarter of 2013.

Utilities that use Sherco 3 say they haven't had to raise rates because replacement power has been available at a reasonable cost.

Powered by WorldNow
All content © Copyright 2001 - 2014 WorldNow and KTTC, a Quincy station.
All Rights Reserved. For more information on this site, please read our Privacy Policy and Terms of Service and Mobile Privacy Policy & Terms of Service.

Persons with disabilities who need assistance with issues relating to the content of this station's public inspection file should contact Administrative Assistant Jodi Neyens at (507) 280-5104. Questions or concerns relating to the accessibility of the FCC's online public file system should be directed to the FCC at 888-225-5322, at 888-835-5322 (TTY) or at fccinfo@fcc.gov.